Post Date:05/15/2026 12:33 PM6/5/26 Update: The traffic signal poles and mast arms have been installed for the new signal at the Boulevard. The contractor will continue to work on traffic signal wiring as well as the concrete median, sidewalk, and curb. The project is anticipated to be completed by the end of the summer. There will be daytime lane closures throughout the duration of construction.Return to full list >>